Chrysler, Dodge, Jeep and Ram Car Dealership
One-story, 34,050 sf Automobile Sales Center on a 12 acre site within Lockport Square
Location
16471 W 159th Street
Project Timeline
Development Plans Approved by City Council on November 20, 2019
Goddard School
10,666 sf Preschool for children 6 weeks to 6 years of age
Location
16523 W 159th Street
Project Timeline
Development Plans approved by City Council on January 16, 2019
Commenced construction in August of 2019
Certificate of Occupancy issued February of 2020
Holiday Inn Express
50,000 sf 3-story Hotel within Lockport Square
Location
16223 W 159th St
Project Timeline
Development Plans approved by City Council on February 20, 2019
Commenced construction in December of 2019
Lock & Mule - Tangled Roots Brewery
6,200 sf Wood Fired Grill Restaurant, Bar, and Brewery on State St
Location
1025 S State St
Project Timeline
Development Plans approved by City Council on July 17, 2019
Commenced Construction in November of 2019
Lockport Animal Hospital
New Build 3,948 sf Animal Hospital at the original location on E 9th Street
Location
1139 E 9th Street
Project Timeline
Development Plans approved by City Council on April 17, 2019
Commenced Construction in September of 2019
Certificate of Occupancy issued in February of 2020
Marcus Cinemas
48,404 sf Movie Theater within Lockport Square
Location
TBD W 159th Street
Project Timeline
Development Plans approved by City Council on January 16, 2019
O'Reilly Auto Parts
7,453 sf Commercial Auto Parts Store in Lockport Crossings
Location
1230 E 9th Street
Project Timeline
Development Plans approved by City Council on December 20, 2017
Commenced Construction in June of 2019